Work in Progress:
- Continuing the wall framing and electrical rough-in in room 101, 104, & 223.
 - Wall framing, electrical & plumbing rough-in continue in the new first floor restrooms.
 - Electrical floor box layout and core drilling has begun in 223.
 - Continuing the wall patch and repair in rooms with removed HVAC (Uni-vent) perimeter wall equipment.
 
Looking forward:
- Start HVAC sheet metal ductwork on the first floor.
 - Planned power outage on 3/19/2016 to make connections to new switchgear.
 - Continue with sanitary and water rough-in in restrooms on the first floor.
 - Complete framing and rough-in for inspections prior to drywall boarding.
 - Continue with wall patching at HVAC (Uni-vent) demolition areas.
 - Demolition of 3rd floor relief air dampers scheduled for spring break.
 - Begin steel lift plan and layout work.