3/17- Cunningham Hall Renovation Updates
	
 
  
    
  
          
            Work in Progress:
	- Chilled water service in the 3rd floor east mechanical room is 95% complete by EOB on 3/18.  Will be ready for cooling system startup on 4/15.
 
	- Currently insulating the chilled water pipes in the 3rd floor wast mechanical room.
 
	- Steam reducing station in the 3rd floor east mechanical room is approximately 10% complete.
 
	- Completed the installation of the temporary roof duct work.
 
	- Electrical demolition work in the tunnels is complete.
 
	- Containment is in place for the abatement of AHU #2 in the 3rd floor west mechanical room.
 
Looking ahead:
	- AHU#2 will be shut down 7:00am-3:00pm for abatement Monday through Thursday (3/21-3/24).
 
	- Roth will be piping the control valves and coils to AHU#1 in the 3rd floor east mechanical room.
 
	- Abatement to start in the 3rd floor ceilings.  Tuner will coordinate with Mark Moser.
 
	- Ceiling grid to be removed on the second floor south west corridor.
 
	- Complete foundations and start retaining wall pours scheduled for 3/22.
 
	- Start foundations and hoistway walls for new elevator.
 
 
      
    
    
 
  POSTED: Thursday, March 17, 2016 12:00 AM
 
    
        
            Updated: Saturday, December 3, 2022 01:02 AM